PrepPilotPrepPilot
PrepPilot™Study Smarter. Pass Faster.™
Question of the DayReadiness ScorePMP® ResourcesPricing
PMP® Resources

PrepPilot™

The AI instructor for the PMP® exam. Study Smarter. Pass Faster.™

PrepPilot LLC · Broomfield, Colorado
support@mypreppilot.com

Product

  • Readiness Score
  • Adaptive Routing
  • Pricing
  • Pass Guarantee
  • How We Get It Right
  • 8th Edition

Compare

  • Compare Tools
  • Best PMP® Prep 2026
  • vs PMI® Study Hall
  • vs PrepCast
  • vs TIA
  • vs Pocket Prep
  • vs Prepsaret

Resources

  • PMP® Resources
  • PMP® Tools
  • Question of the Day
  • Our Story
  • What's New

Legal

  • Terms of Service
  • Privacy Policy
  • Cookie Preferences
© 2026 PrepPilot LLC

PMP® and PMBOK® are registered marks of the Project Management Institute, Inc. PrepPilot™ is not affiliated with, endorsed by, or sponsored by PMI.

PrepPilotPMP® ToolsPERT Estimator

Free PMP® PERT Calculator

Three-point estimation using PERT (beta) or triangular distribution. Enter optimistic, most likely, and pessimistic durations to calculate expected duration, standard deviation, and confidence ranges.

Activity Inputs
Method:

PERT Formulas Explained

PERT (Beta Distribution)

tE = (O + 4M + P) / 6

Gives 4x weight to the most likely estimate. This is the formula PMI uses on the PMP® exam unless stated otherwise. The “4” reflects the beta distribution assumption.

Triangular Distribution

tE = (O + M + P) / 3

Gives equal weight to all three estimates. Use when there is no reason to weight the most likely value more heavily. Less common on the PMP® exam but still fair game.

Standard Deviation

σ = (P - O) / 6

Measures the spread of uncertainty. A wider gap between optimistic and pessimistic means more risk. This formula is the same for both PERT and triangular methods.

Variance

σ² = [(P - O) / 6]²

The square of the standard deviation. Critical for multi-activity aggregation: you sum variances across activities, then take the square root for the combined standard deviation.

Multi-Activity Aggregation

Total Expected = Σ tE

Total Variance = Σ σ²

Combined σ = √(Total Variance)

When estimating a project with multiple activities on the critical path, sum the expected durations and sum the variances (not the standard deviations). Then take the square root of the total variance to get the project-level standard deviation. This assumes activities are independent.

Common Exam Traps
  • Adding standard deviations instead of variances. You cannot add σ values directly. Always sum σ² first, then take the square root for the combined σ.
  • Confusing PERT with triangular. PERT uses (O + 4M + P) / 6, triangular uses (O + M + P) / 3. The exam will say “three-point estimate” and expect you to know which formula applies. Default to PERT unless told otherwise.
  • Mixing up sigma levels. ±1σ = 68.3%, ±2σ = 95.5%, ±3σ = 99.7%. The exam may ask “what is the range at 95% confidence?” which maps to roughly ±2σ.
  • Forgetting that σ = (P - O) / 6 is the same for both methods. Only the expected value formula changes between PERT and triangular. The standard deviation calculation is identical.

Want to practice these formulas under exam conditions? Try 10 free PMP® practice questions or explore more PMP® study resources.

Frequently Asked Questions

What is PERT estimation?

Program Evaluation and Review Technique (PERT) is a three-point estimation method that calculates an expected duration from optimistic (O), most likely (M), and pessimistic (P) values to account for uncertainty.

What is the PERT formula?

Expected duration = (O + 4M + P) / 6. Standard deviation = (P − O) / 6. The 4× weighting on the most likely value produces a beta distribution.

How is PERT different from triangular estimation?

Triangular estimation uses (O + M + P) / 3, weighting all three points equally. PERT (beta) weights M four times more heavily, which produces a tighter, more realistic forecast when the most likely value is well understood.

When should I use PERT on the PMP® exam?

Use PERT when uncertainty is high and a single estimate would be misleading. The exam expects you to recognize PERT as the more rigorous of the two three-point techniques and to calculate expected duration and standard deviation cleanly.

How often does PERT appear on the 2026 PMP® exam?

PERT and other estimation techniques sit in the Process domain (41% of the 2026 exam). Expect calculation questions and concept questions on when to use PERT vs analogous, parametric, or triangular estimates.

Related Tools

EVM CalculatorCritical Path CalculatorCommunication Channels

Practice PMP® formulas with PMP® exam-style practice questions

10,000+ questions · AI-powered coaching · Free to start